Whitecross have been retained by APAM on Optima Building, Glasgow for the last 6 years to undertake regular Planned Preventative Maintenance works and provide building surveying advise and defect pathology.

Client:

APAM

Our Role:

The project was involved all works being completed while the premises were fully occupied and included out of hours working.

Our services in summary comprised:

  • Production and annual review of the Planned Preventative Maintenance Programme.
  • Adopted the role of Contract Administrator and Cost Consultant in respect of Annual PPM Works.
  • Adopted the role of Principal Designer in execution of Client duties under CDM Regulations.
  • Cost reporting and management of works to completion.