Project Summary

Due to a period of accelerated growth, Spire Global UK Ltd needed the infrastructure to cope with increased headcount and thus a much larger production facility.

Client:

Spire Global UK Ltd

Our Role:

Having kicked off pre-covid, the project was made more complex with the need to have more covid-resilient desk space. This took the form of movable dividers for covid compliance, better ventilation in meeting rooms, and more break-out pods.

The result was a beautifully designed and built space, fit for purpose with room to grow alongside their headcount. This included:

  • Full Cat-B fit-out with Cat-A alterations
  • Furniture Procurement
  • New cleanroom facility
  • Floor finishing
  • IT Integration

The project was delivered on-budget, and despite design-work being completed over Teams, the project was delivered in a timely manner. The client was extremely happy, and an existing relationship was strengthened.

Gary Grantham, Business Operations at Spire Global UK Ltd said about the project:

I’d like to personally thank Kevin Miller and all the team at Whitecross for delivering this project for Spire, on time and on budget.

Our business had very specific requirements factored into the scope of this project and these were skilfully and intuitively woven into the fit out. We’re delighted with the final results and our team in Glasgow now have the office that helps showcase their talents to the best of their ability

Want to know More?

Would you like to know more about this project? Feel free to contact Kevin to discuss your requirements.
-
Tel: 0141 332 1552
kevin.miller@whitecrossbc.co.uk
LinkedIn Profile
Our Experience View All Projects